NOTE:
The DSC OFF switch is integrated with the cluster switch.
For the DSC OFF switch removal/installation, refer to CLUSTER SWITCH REMOVAL/INSTALLATION. (See CLUSTER SWITCH REMOVAL/INSTALLATION.)
1. Remove the cluster switch. (See CLUSTER SWITCH REMOVAL/INSTALLATION.)
2. Verify that the resistance between cluster switches B and C is as indicated in the table.
If the resistance cannot be verified as indicated in the table, replace the cluster switch.
3. Apply battery positive voltage to cluster switch terminal J, and connect terminal I to ground.
4. Verify that the LED illuminates.
If there is any malfunction, replace the cluster switch.